"I am quite taken aback by the generosity shown to me by ESI. Thank you very much, and of course I shall think of the great things we accomplished here at Boardman together. We are equally proud of your buildings here as they grace our plant and I sincerely hope that there are more opportunities in the future for us to fashion more great buildings together. Your supervisor has been magnificent in his support of Pacific Ethanol here on site, and proved to be a willing and able partner to us through the tough times as well as the good. He has served ESI well here. Thank you again and my very best wishes for the future."
- Michael PJ O'Donoghue, Onsite Construction Manager, Pacific Ethanol Inc.
Owners Pacific Ethanol, Inc.
Operations Ethanol Production Facility with a plant capacity of 40 million gallons per year.
Structure Four custom engineered steel building systems totaling 54,400 square feet: Wetcake, Boiler, Main Processing and Administration Buildings |
General Contractor ESI Construction
Design Ford Bacon Davis Engineering
Awards American Buildings Company, Industrial Design/Build Award of Excellence |
|

 |
The Columbia Trailer facility is two buildings totaling 34,753 square feet, with three attached lean-to structures totaling 8,540 square feet. Eight bridge cranes and seventeen jib cranes were integrated into the designed for use in the manufacturing area. 8'-0" high concrete tilt wall panels provide protection in the manufacturing area from equipment and materials handling. A change in the roof line and a 3'-0" CMU wall delineates the office area from the plant.
Operations Manufacturing plant, distribution center, warehouse and offices
Floor Area 30,0000 square feet
Structure Pre-engineered steel systems construction |
Systems Contractor ESI Construction
Design Group Mackenzie
Awards Metallic Buildings Company – Outstanding Design and Construction Award |
|

 |
Owner Larry Morris
Operations FedEx Ground coastal distribution facility
Floor Area 8,300 square feet
Structure Custom Engineered Steel Building System |
Systems Contractor ESI Construction
Design ESI Construction
|
|

 |
Winner of ABC's project of the year, this three story office, warehouse, manufacturing, and parking complex was a design build project. The pre-engineered steel clearspan building incorporates concrete tilt wall panels 7'-4" high around the perimeter, integrated with metal panels and a standing seam metal roof. This combination takes advantage of the best features both materials have to offer; the durability of concrete and the performance, efficiency and economy of steel.
Operations Manufacturing plant, distribution center and ware house with three story office and parking
Floor Area 52,736 square feet
Structure Two story, pre-engineered steel systems construction
Contractor ESI Construction
Design ESI Construction |
Awards A&S Buildings Systems – Design/Build Award
Associated Builders and Contractors Excellence In Construction – 1st Place Systems Construction Over $2 Million
Associated Builders and Contractors – President's Award
Associated Builders and Contractors, Excellence in Construction – 1997 Project of the Year |
|

 |
"Thank you for your exceptional performance on the Halawa Heights project. Your expertise of steel building design adn construction made this difficult job run as smoothly as it did. This was our third project together and we know without a doubt that we have the right contractor on our team." - George Kashiwa, Partner, TGY & Associates
Owners TGY & Associates
Operations Manufacturing, warehouse, office space, and parking garage with car ramp
Floor Area 92,703 square feet
Structure Three story, pre-engineered steel systems construction |
Contractor ESI Construction
Design Herb Nakano, P.E.
Awards ABC Excellence in Construction
1st Place, Systems Construction over $2 million
A&S Buildings Company
Award of Merit
|
|

 |
The light industrial park utilizes excess, vacant land the owner had in Tigard, OR. The project features a single tenant pad building and a larger multi-tenant building designed to accommodate four separate businesses. Both energy efficiency structures utilize Butler Building systems combined with natural split-faced, concrete masonry wainscoting. The project was designed to provide the maximum lease space allowed on the site with the lowest long-term maintenance and operating costs.
Owners T-3 Enterprises
Operations Light industrial leasable space
Floor Area 19,166 square feet
Structure Butler pre-engineered steel system with MR–24 roof |
General Contractor ESI Construction
Design ESI Construction
Awards Butler Industrial Award of Excellence |
|
|
|